๐๐๐ฆ๐ ๐๐ข๐ญ๐ฒ ๐จ๐ ๐๐๐ฆ๐ฅ๐จ๐จ๐ฉ๐ฌ ๐ฉ๐ฅ๐๐ฒ๐๐จ๐จ๐คโ๐๐ฅ๐๐ฆ๐ ๐ญ๐ก๐ ๐๐๐ ๐๐จ๐ฎ๐ซ๐ญ ๐๐ก๐๐ฅ๐ฅ๐๐ง๐ ๐ ๐๐จ๐ซ โ๐๐๐ฅ๐๐ฒ ๐๐จ๐ฌ๐ญ๐ฌโ ๐ข๐ง๐ฌ๐ญ๐๐๐ ๐จ๐ ๐จ๐ฐ๐ง๐ข๐ง๐ ๐ซ๐ข๐ฌ๐ข๐ง๐ ๐ฉ๐ซ๐จ๐ฃ๐๐๐ญ ๐๐จ๐ฌ๐ญ๐ฌ.
The City states the AAP court challenge resulted in a 6-month delay and $4โ5M in Multiplex costs due to tariffs and economic uncertaintyโbased on vague โinflationary assumptions,โ not a clear, itemized cost breakdown.
But the timeline doesnโt support the claim:
- Oct 22, 2024; AAP petition filed
- Feb 21, 2025: Court decision
The court process took about 4 monthsโnot 6โand included Christmas/New Yearโs, when work slows or pauses.
The original 2025 timeline (now quietly replaced on the website) confirms the project was still in validation and design during this period.
Construction wasnโt scheduled to start until fall 2025.
So what was actually delayedโor exposed to inflationโto justify $4โ5M in added costs, when the project was still in validation and designโnot in procurement or construction?
The City points to tariffs and โeconomic uncertaintyโโbut those affect every project.
Meanwhile, the project keeps growingโand so do the costs:
- Library added after the AAP
- Possible mini-rink
- Ongoing design refinement
- Site challenges
๐๐ก๐ ๐ฉ๐ฎ๐๐ฅ๐ข๐ ๐๐ฌ๐ค๐๐ ๐๐จ๐ซ ๐๐๐๐จ๐ฎ๐ง๐ญ๐๐๐ข๐ฅ๐ข๐ญ๐ฒโ๐ญ๐ก๐ข๐ฌ ๐ข๐ฌ๐งโ๐ญ ๐ข๐ญ.

Read the Castanet article here: Delays, new features push cost for City of Kamloops arena multiplex past $154M